Another progressive week with the grey float set to the front, rear and alfresco pillars.
They have also started white plaster rendering to the internal walls, starting from the front rooms, passage way, study, home theatre and master suite. The living areas and kitchen were not done yet.







Wall waiting for dry lining repair.

White plaster to the master suite entrance and into the walk-in-wardrobe.

Home theatre white plastering 90% done.

Study almost done.

Celeste's room looks good.

Caleb's room all done.

Front passage wall all rendered.

A little bit more to do on the activity room wall by the window.

Living area walls were not rendered yet.

Lounge and dining area walls waiting for white plaster.